Financing observatory

What a m³/day of biomethane costs in Brazil

The biomethane deals approved by BNDES disclose the amount financed, often the total investment, and the plant capacity. Together they form the first Brazilian capital cost curve, with one source per deal.

Deals
7
BNDES financing
R$1.1BSum of what was disclosed
From the Climate Fund
R$428.2MSum of what was disclosed
Combined capacity
501,481m³/day

Landfill

Upgrading the biogas the landfill already captures, compression and connection.

R$1,978 to R$2,596

per m³/day of capacity, 3 deals with total investment

Agro-industrial

Includes the digester, not just upgrading: vinasse, effluents and agro-industrial residues.

R$4,116 to R$6,504

per m³/day of capacity, 2 deals with total investment

The deals

Levelised capital: R$ per m³ produced, capital only, with a 20-year life, a 90% capacity factor and a 10% and 12% cost of capital.

ProjectRouteCapacity (m³/day)CAPEX per m³/dayCapital per m³Source
Gás Verde Igarassu (PE)total investment · 2025-05Landfill45,600R$1,978R$0.71 to R$0.81Source
Onebio / Biometano Verde Paulínia (Edge + Orizon) (SP)financing only: a lower bound · 2025-12Landfill225,000≥ R$2,000R$0.72 to R$0.82Source
GNR Mauá (Lara + MDC Energia) + GNR Vila Velha (Lara + MDC Energia) (SP/ES)total investment disclosed jointly · 2026-09Landfill97,000R$2,526R$0.90 to R$1.03Source
Biometano São Leopoldo (Solví) (RS)total investment · 2025-07Landfill36,744R$2,596R$0.93 to R$1.06Source
Tropical Biogás (bp bioenergy) (GO)total investment · 2026-04Agro-industrial67,000R$4,116R$1.47 to R$1.68Source
Bioo Paraná (PR)total investment · 2026-02Agro-industrial30,137R$6,504R$2.33 to R$2.65Source

Limits

  • These are press releases and news reports, not the contracts. Each row cites its source; the values should be checked against BNDES open data before they become a reference.
  • When the total investment was not disclosed, the amount financed counts as a lower bound and stays out of the ranges by route.
  • A landfill's investment covers what the project needs (upgrading, compression, connection); the biogas capture may already exist. It does not compare with a project that starts from scratch.
  • Levelised capital leaves out operation, maintenance and feedstock. Cost of capital, life and capacity factor are assumptions.